The $15 million Schenectady, New York, Amtrak train station has a new schedule.

It will be built in two phases. The first, costing $6 million, will be concrete and structural. The second phase, starting this fall, will cost $9 million.

Bids will be sought in February and awarded in March. The project on Erie Boulevard will be finished November 2018.

The original estimated completion date was spring 2018.

The project will replace the existing aging, cramped station.

The overall project was scaled…